2026/03/23: Lockot / Tagout SOP
Document Number: LOTO/01
Version: 01
Compiled By: Dean Jacobs
Review Date: 2027/03/23
1. PURPOSE
To establish a safe and controlled procedure for isolating hazardous energy sources during maintenance and servicing activities to ensure:
2. SCOPE
This procedure applies to:
It covers:
3. LEGAL COMPLIANCE
This SOP complies with:
4. DEFINITIONS
5. ROLES AND RESPONSIBILITIES
Maintenance Manager / Safety Officer (Dean Jacobs)
Maintenance Supervisor
Authorized Employees
Affected Employees
6. WHEN LOTO MUST BE APPLIED
LOTO is mandatory when:
7. LOTO PROCEDURE
Step 1: Preparation
Step 2: Shutdown
Step 3: Isolation
Step 4: Lockout/Tagout
Step 5: Release Stored Energy
Step 6: Verification
Step 7: Perform Work
Step 8: Removal of LOTO
8. GROUP LOCKOUT
9. CONTRACTOR CONTROL
10. EQUIPMENT REQUIREMENTS
LOTO equipment must include:
11. TRAINING REQUIREMENTS
All relevant personnel must be trained in:
Refresher training must be conducted periodically.
12. INSPECTIONS AND AUDITS
13. NON-COMPLIANCE
14. RECORD KEEPING
The following must be maintained:
15. REVIEW AND REVISION
This SOP must be reviewed: