πŸ“‹ JC-202606-0027 Closed
Fault ref: MAINT-202606-0025  |  Area: Wholesaler
100%
100% complete
πŸ“Œ Job Details
Manager
Dean Jacobs
Technician
Peet Schutte
Reported by
Gudrun de Bruyn
Priority
Medium
Est. completion
18 Jun 2026
Materials
Partial
πŸ”΄ Original Fault
Kan ons asseblief die volgende:

β€’ 5 – 6 Rakke in kerk area, langs die Huidige rakke; vir nuwe voorraad;
β€’ 2 x aansteek borde (soos by my werk stasie) – Een by Pick start rekenaar en een by Frontshop. Die verf verniel met alles wat teen die mure geplak word. (90cm x 70cm)
πŸ”§ Work to be Done
Peet will inspect the area to determine the shelving requirements, including the necessary anchoring materials and installation requirements for the additional racks in the church area.

He will also obtain a quotation for the supply and installation of 2 x notice boards (90cm x 70cm), one for the Pick Start computer area and one for the Front Shop.
🧰 Materials
MaterialQtyAvailableOrderedArrived
Pin Boards 2 No β€” 07 Jul 2026
Rawl bolts 20 Yes β€” β€”
Shelf's 5-6 Yes β€” β€”
🧰 Stock Requests
No stock has been requested for this job yet. Use "Update Job Card" to request stock β€” it needs to be approved here before it's deducted from on-hand.
⏱ Timeline
Fault reported
11 Jun 2026 13:35
Job card created
11 Jun 2026 13:39
⏱ 4m after fault
Work started
26 Jun 2026 05:32
Work completed
31 Jul 2026 10:54
⏱ Total job time: 49d 21h
Closed
31 Jul 2026 10:54
⏱ 49d 21h fault to close
✍️ Sign-Off
Manager Signature
Dean Jacobs
Assistant Signature
Peet Schutte
πŸ“ Notes
Good day please note that we are left with two shelf's to build, which will be completed this week
⭐ Customer Rating
Awaiting feedback from the person who reported this issue.
πŸ–¨οΈ Print / Email 🧾 Raise Work Order ← Back to Fault πŸ“‹ Register