📌 Job Details
Manager
Dean Jacobs
Technician
Petrus Manko
Reported by
Dean Jacobs
Priority
Medium
Est. completion
—
Materials
Yes
🔴 Original Fault
Last test
📷 Reported Photo
🔧 Work to be Done
Fillters needz replacing
🏭 Supplier
Supplier
Jacks Paint
Contact
Fannie - 081 470 9327
Order date
—
🧰 Stock Requests
No stock has been requested for this job yet. Use "Update Job Card" to request stock — it needs to be approved here before it's deducted from on-hand.
⏱ Timeline
Fault reported
25 Aug 2026 08:47
Job card created
25 Aug 2026 08:47
⏱ 0m after fault
Materials ordered
25 Aug 2026 08:51
Materials arrived
25 Aug 2026 08:50
⏱ 1m delivery time
Work started
25 Aug 2026 08:52
Work completed
25 Aug 2026 08:52
⏱ Total job time: 4m
Closed
25 Aug 2026 08:53
⏱ 6m fault to close
📷 Photo of Completed Work
✍️ Sign-Off
Manager Signature
Dean Jacobs
Supervisor Signature
Peet Schutte
Technician Signature
Petrus Manko
Assistant Signature
Paul Phatswane
⭐ Customer Rating
Awaiting feedback from the person who reported this issue.